Home IPSO Help IPSO Help Business As Usual (BAU) Projects
|
|
Business As Usual (BAU) Projects |
|
What is a BAU activity
Setting up a BAU project - example
Data entry by Users into a BAU project
Reporting off BAU projects
BAU covers activity that is non-project related.
For example, a software engineer might be seconded to a project
team and is also responsible for assisting the Help desk as and
when certain support calls are received. Setting up the Help desk
as a BAU will allow the engineer to record time spent on support
calls. It would be useful, for example, to look at what time
support calls have taken up, at the expense of time that was
originally assigned to be spent on projects.
The essential difference between a BAU activity and a normal
project is that in BAU it is the User him/herself that assigns the
activity, whereas in a normal project, the Manager or Stage Manager
assigns tasks.
- Create a Project as normal
- Set Start and Finish dates - normally something like a 12-month
period.
- Check In and store the Project to the Server
- Create Sub-Tasks
- Move each task to the state “In Progress”
- Create if necessary a User Group which can be used to identify
people who will use this BAU task. For example “HELP DESK
STAFF”.
- In Project | Properties - Advanced tab tick BAU project
- Staying in Project | Properties - Advanced tab select the
Public Group for the BAU Project from the drop-down list (in this
case the specially created Group called HELP DESK STAFF)
Users, who are a member of the User Group, can now record
themselves the time taken on the different activities:
- View | BAU projects
- The Project and subtask(s) will appear. Select the Sub-task
against which the work is to be recorded.
- Right Click and select “Assign Me”
-

- Enter duration, date and notes describing the activity
-

- Press OK to enter the details
The following report shows, for each person who has recorded
activities against the BAU project, how much time he/she spent and
on what activity.

(The above report was created using Rows tab entry Accounts -
TodoItems)
Using Help File
|
|